Erratum: Contrary to what was announced in the last update (Upgrades are stopped until 19/09/2024), the upgrades resumed on 16/09/2024 and are still in progress.
Here is the progress per cluster: ca001: 100% eu001: 89% eu002: 29% eu004: 89% eu007: 78% eu008: 37% eu009: 96% eu010: 98% eu011: 95% eu013: 96%
We apologise for any inconvenience caused.
Posted Sep 18, 2024 - 17:51 UTC
Update
Please find below the details of the database upgrade.
Upgrades have resumed since 2024-08-12. The clusters being upgraded are eu001 and eu007. We expect to finish both at the end of the next week.
Posted Aug 20, 2024 - 08:31 UTC
Update
We are pleased to inform you that 727 instances are now running on MySQl database. The upgrades are now paused, and will continue on 12/08/2024.
Posted Jul 25, 2024 - 17:13 UTC
Update
75 instances are now running MySQL database on Cluster eu010. The upgrades are now paused for the week-end, and will continue on 22/07/2024.
Posted Jul 18, 2024 - 18:21 UTC
Update
40 instances are now running MySQL database on cluster eu010
Posted Jul 18, 2024 - 08:38 UTC
Update
1230 databases are now running MySQL database on cluster eu010.
Posted Jul 11, 2024 - 10:16 UTC
Update
Update : Our teams have updated 120 databases
Posted Jul 10, 2024 - 09:04 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 10, 2024 - 08:00 UTC
Scheduled
As part of our continuous improvement plan, maintenance is scheduled on our databases.
This may temporarily affect availability.
Start time : 10/07/2024 08:00 UTC End time : 30/09/2024 12:00 UTC Service impact : A 1 minute downtime is expected. Service improvement : We are going to upgrade MySQL 5.7 to MySQL 8.0 The goal of this maintenance is to improve the performance and enhance the security of our infrastructure.
The upgrades will occur every Monday, Tuesday, Wednesday and Thursday. Progress will be posted here.
The maintenance work will be carried out in 2 phases. The first phase will begin on: Start time : 10/07/2024 08:00 UTC End time : 25/07/2024 12:00 UTC
The second phase will begin on: Start time : 12/08/2024 08:00 UTC End time : 30/09/2024 12:00 UTC Progress will be posted here.
Thank you for your understanding.
Posted Jul 09, 2024 - 16:26 UTC
This scheduled maintenance affected: Web Hosting || Databases GRA (eu001, eu002, eu004, eu007, eu008, eu009, eu010, eu011, eu013) and Web Hosting || Databases BHS (ca001).