In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 20, 2025 - 22:00 UTC
Scheduled - As part of our continuous improvement plan, maintenance is scheduled on our Web Hosting Offer.
Start time : 20/01/2025 22:00 UTC
End time : 21/01/2025 03:00 UTC
Service impact : Special services net2ftp and phpmyadmin are temporary unavailable on Cluster023 during this maintenance
Filerz below will be unavailable one by one during 20 minutes.
Cluster013- Filerz298
Cluster023 - Filerz105
Cluster023 - Filerz122
Cluster023 - Filerz981
Cluster020 - Filerz17
Service improvement : We are going to reboot the Filerz one by one (Web Hosting server) to improve the performance and stability of the service.
Thank you for your understanding.
Jan 20, 2025 22:00 - Jan 21, 2025 03:00 UTC
Identified - We have determined the nature of the incident affecting .in domains since 15/01/2025 10:30 UTC.
Here is detail for this incident:
Start time : 15/01/2025 10:30 UTC
Service impact : Customer with a .in domains name are unable to perform some tasks.
Ongoing actions : The incident has been identified, and our teams are mobilized to restore service as quickly as possible.
Our teams are fully engaged and working to resolve the issue as quickly as possible. We will keep you updated on the progress and resolution.
We apologize for any inconvenience caused and appreciate your understanding.
Jan 20, 2025 - 09:21 UTC
Investigating - An incident is in progress on our Web Cloud in Global, customers in the impacted zone may face some difficulties. Please find the details:
Start time : 15/01/2025 10:30 UTC
Service impact : Customer with a .in domains name are unable to perform some tasks.
Ongoing actions : Our teams are actively working to resolve the incident and restore services as quickly as possible.
We will keep you informed of developments and the resolution of the incident.
We apologize for the inconvenience and thank you for your understanding.
Jan 15, 2025 - 10:52 UTC
Update - 50% of the cluster had been successfully upgraded.
The upgrades will continue on 20/01/2025.
Jan 17, 2025 - 16:45 UTC
Update - The upgrades stopped at 19:49 UTC.
28% of the cluster had been successfully upgraded.
The upgrades will continue on 15/01/2025.
New end time : 23/01/2025 21:00 UTC
Jan 07, 2025 - 20:05 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 07, 2025 - 08:44 UTC
Scheduled - As part of our continuous improvement plan, maintenance is scheduled on our Database offer.
Start time : 07/01/2025 08:00 UTC
End time : 07/01/2025 21:00 UTC
Service impact : 1 minute downtime per customer
Service improvemen : Following our continuous improvement policy, we are doing an upgrade on Debian.
Thank you for your understanding.
Jan 7, 2025 08:46-21:16 UTC
Update - Please note that 25% of the migration has now been completed.
We will continue to keep you updated as we move forward.
Jan 16, 2025 - 19:09 UTC
In progress - Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jan 15, 2025 - 11:46 UTC
Update - We will be undergoing scheduled maintenance during this time.
Jan 15, 2025 11:46 - Jan 30, 2025 22:00 UTC
Scheduled - As part of our continuous improvement plan, maintenance is scheduled on our Database offer.
Start time : 15/01/2025 10:46 UTC
End time : 30/01/2025 21:00 UTC
Service impact : 1 minute downtime per customer
Service improvemen : Following our continuous improvement policy, we are doing an upgrade on Debian.
Thank you for your understanding.
Jan 15, 2025 11:46 - Jan 30, 2025 22:00 UTC