Start time : 15/03/2023 21:00 UTC End time : 15/03/2023 21:50 UTC Service impact : Unavailability of the filerz for around 30 minutes during the migration. Service improvement : Following our continuous improvement policy, we are going to migrate the filerz701 to keep our infrastructure up-to-date.
Posted Mar 15, 2023 - 21:51 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 15, 2023 - 21:00 UTC
Scheduled
Start time : 15/03/2023 21:00 UTC End time : 15/03/2023 23:00 UTC Service impact : Unavailability of the filerz for around 30 minutes during the migration. Service improvement : Following our continuous improvement policy, we are going to migrate the filerz701 to keep our infrastructure up-to-date.
Posted Mar 09, 2023 - 20:04 UTC
This scheduled maintenance affected: Web Hosting || Datacenter GRA (Cluster026).