Start time : 04/09/2023 01:32 UTC End time : 04/09/2023 10:35 UTC Root cause : Network issue. Our technical teams resolved the issue. All impacted services are now operational.
Posted Sep 04, 2023 - 10:44 UTC
Identified
Start time : 04/09/2023 01:32 UTC Service impact : Slowness is being observed for some hosted websites on Cluster024 Root cause : Network issue. Ongoing actions : Our technical teams are fixing the issue.
Posted Sep 04, 2023 - 05:22 UTC
Investigating
Start time : 04/09/2023 01:32 UTC Service impact : Slowness is being observed for some hosted websites on Cluster024 Ongoing actions : Our technical teams are investigating the issue. Update will be posted as significant progress is made.
Posted Sep 04, 2023 - 01:48 UTC
This incident affected: Web Hosting || Datacenter GRA (Cluster024).